Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 576     Entry time: 07 Nov 2018, 10:44
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Karabo was updated yesterday. Test is ongoing. So far no issues.
  • The macros for cooling down and warming up the detector do not work properly. If the button is pushed twice the setpoint changes continuing e.g. cooling down too much. Marcin will bring the issue up with CAS (HS).

 

FXE

SQS

SCS

  • Issue was found with Elmo controllers crates: due to a problem in the EPLAN macro the ground is not connected to the motor cables. The mitigation strategy will be discussed by PG, LW, MF and MT in a meeting.

 

MID

  • AGIPD will move in the hutch today.
  • PCs are being installed. Karabo need to be deployed.

HED

XPD

 

​​VAC

AE

TDM

CAS

  • Karabo 2.3 is now a release candidate. Testing ongoing.

AoB