Message ID: 265     Entry time: 29 May 2017, 16:30
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 meeting 

 General

  • Photon tunnels are open until Wednesday afternoon due to the flooding on the weekend. 
  • The down time should be used to do important fixes/upgrades
  • XTD9 can stay open all week depending on the decision of the PCT
  • Photon commissioning successfully brought beam to the end of both the SPB and FXE beam lines

XTDs

  • Stability problem of SR imager is still being worked on by A. Parenti (CAS)
  • A new version of Karabo with many fixes is currently being tested and will be deployed once the test results appear satisfactory
  • Test of the PBLM motors still need to be done in XTD9. This requires an update of the motion loop that should be done today or tomorrow
  • There is also the need of an update of the vacuum loop. This should also be done during the down time

FXE

  • Problem still exist with vacuum controls. The problem appears to be understood and seems to be on the PLC side. FXE uses ion pumps with an analog output that does not interface with the alarm level settings.J. Tolkiehn is working on it
  • Work progresses on motor testing
  • FXE requests firmware for loop 7. But this work interferes with the priority on the vacuum.

SPB

  • Loop 1 is now fully available with all modules
  • Loop 2 is available with only the first module. The other modules are away for modification
  • Due to the flooding the connectors cannot be attached until cables have dried and have been re-tested

PLC

  • AE will work again on AGIPD this week. This limits resources for the instruments

KARABO

  • Problem with X2 timer interface is solved. But PCT apparently still uses the DOOCS interface.
  • Waiting for the go ahead to release the next KARABO version
  • Work progresses in parallel to intergrate DAQ into KARABO. This will be the next version after the bug-fix version

ITDM

  • The announced update of the network switches will be  done on Tuesday morning and will result in a 5 minute network interrupt

 