Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 265
Entry time: 29 May 2017, 16:30
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
General
- Photon tunnels are open until Wednesday afternoon due to the flooding on the weekend.
- The down time should be used to do important fixes/upgrades
- XTD9 can stay open all week depending on the decision of the PCT
- Photon commissioning successfully brought beam to the end of both the SPB and FXE beam lines
XTDs
- Stability problem of SR imager is still being worked on by A. Parenti (CAS)
- A new version of Karabo with many fixes is currently being tested and will be deployed once the test results appear satisfactory
- Test of the PBLM motors still need to be done in XTD9. This requires an update of the motion loop that should be done today or tomorrow
- There is also the need of an update of the vacuum loop. This should also be done during the down time
FXE
- Problem still exist with vacuum controls. The problem appears to be understood and seems to be on the PLC side. FXE uses ion pumps with an analog output that does not interface with the alarm level settings.J. Tolkiehn is working on it
- Work progresses on motor testing
- FXE requests firmware for loop 7. But this work interferes with the priority on the vacuum.
SPB
- Loop 1 is now fully available with all modules
- Loop 2 is available with only the first module. The other modules are away for modification
- Due to the flooding the connectors cannot be attached until cables have dried and have been re-tested
PLC
- AE will work again on AGIPD this week. This limits resources for the instruments
KARABO
- Problem with X2 timer interface is solved. But PCT apparently still uses the DOOCS interface.
- Waiting for the go ahead to release the next KARABO version
- Work progresses in parallel to intergrate DAQ into KARABO. This will be the next version after the bug-fix version
ITDM
- The announced update of the network switches will be done on Tuesday morning and will result in a 5 minute network interrupt
|