Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 480
Entry time: 26 Feb 2018, 12:09
|
Author: |
Monica Aresté |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 26.02 |
|
|
SPB:
- Ion pumps running in the Mirror chamber.
- Starting test with mirrors together with CAS this week.
- In general everything in good position to receive beam.
- Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to have the primary limits included. This will suppose a hardware modification.
AE:
- SASE3: train IDs in loop2 are working, the problem was fixed last Friday.
ITDM:
- Measurements for commissioning continues.
CAS:
- H.Santos inform that CAS has not resources to run tasks for SASE2, this might affect the date for first lasing in SASE2. Priorities are SASE1 operation and SASE3 commissioning.
- G. Wellenreuther will bring this topic to the PSO meeting.
FXE/VAC/Detector/XPD: nobody attended
|