Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
SPB
SQS
XO
ToBeMigrated2XWiki
ToBeMigrated2GitlabPages
ToBeMigratedByGroup
Migrated2Zulip
Archived2PDF
not2MigrateOrArchive
SCS
SXP Migrated2Zulip
Photon Commissioning Team
XRO
DOC
HED Migrated2Zulip
WP74
MID
PSPO_XO
XO_Operation
SQS Migrated2Zulip
FXE Migrated2Zulip
DET
Sample Environment
SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness
Technical integration and coordination
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
480
Entry time:
26 Feb 2018, 12:09
Author:
Monica Aresté
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 26.02
SPB:
Ion pumps running in the Mirror chamber.
Starting test with mirrors together with CAS this week.
In general everything in good position to receive beam.
Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to have the primary limits included. This will suppose a hardware modification.
AE:
SASE3: train IDs in loop2 are working, the problem was fixed last Friday.
ITDM:
Measurements for commissioning continues.
CAS:
H.Santos inform that CAS has not resources to run tasks for SASE2, this might affect the date for first lasing in SASE2. Priorities are SASE1 operation and SASE3 commissioning.
G. Wellenreuther will bring this topic to the PSO meeting.
FXE/VAC/Detector/XPD:
nobody attended