Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 434     Entry time: 13 Dec 2017, 16:28
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1 Status/SASE3 Readiness Meeting 

General

  • Meeting on Friday will take place at 1300 due to overlap with XDAC
  • M. Areste shall ask for updates on task list on Thursday

Instruments

  • SPB
    • Work on AGIPD is ahead of schedule. Closing of detector should happen at the beginning of next week
    • Additional installations for roughing pump system is going on and will probably finish this year

Tunnels

  • Diagnostics group currently working in the Southern tunnels, cabling components and aligning imagers
  • Colleagues from Russia are coming 3 - 20 Jan to work on MCP in SASE3
  • KMono local tests in SASE3 should also happen in early Jan
  • Diagnostics requests scenes for XGM in XTD1

AE

  • Vacuum loop in SASE3 will be modified. Some components shall be moved to a separate loop, e. g. Soft Mono
  • SPB tunnel loop will be re-deployed to include the attenuator
  • The motion loop in SASE1 will also be split to allow more rapid updates for newly integrated components
  • Z-motion crate for detector in SPB will be done until next week or early next year

CAS

  • Currently working with AE and ITDM on refining release schedule for KARABO
  • Testing the version for release next week. This will then first be used by ITDM and is needed for the firmware upgrade of AGIPD
  • Work is going on on the XGM train ID problem
  • FXE will be moved to a separate topic (broker) to disentangle some dependencies at least temporarily
  • FEL imager performance problem was investigated. This runs on a server that is very busy and should be moved to a different server