SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 338
Entry time: 19 Jul 2017, 10:11
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Schedule after 09:30 meeting |
|
|
General
- The latency observed by SPB in the GUI client could be reproduced by CAS. Also a potential reason was identified. As soon as this has been sufficiently tested it will be released
- DAQ tests in FXE with LPD worked for the first time yesterday for 1/16 of the detector
- FXE and SPB will show 1-2 slides about progress and ongoing work during the TC meeting on Friday morning
XTDs
- Fast valve in XTD9 still has issues with noise and will probably need to remain disabled
FXE
- Interlock for loop 1 was deployed. Still need to do loop 2. Work per loop requires ca. 3-4 h.
SPB
- Firmware for the AGIPD hv power supply was updated. The spikes during ramping are gone
- Next items to get going are the SMARAGD motors
- Loop 7 needs to be brought back. Crate 51 has been fixed.
- Work on in vacuum interlock in SPB will need to be carefully timed and coordinated after finishing FXE. Due to impending beam probably not before next week
|