Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 338     Entry time: 19 Jul 2017, 10:11
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Schedule after 09:30 meeting 

General

  • The latency observed by SPB in the GUI client could be reproduced by CAS. Also a  potential reason was identified. As soon as this has been sufficiently tested it will be released
  • DAQ tests in FXE with LPD worked for the first time yesterday for 1/16 of the detector
  • FXE and SPB will show 1-2 slides about progress and ongoing work during the TC meeting on Friday morning

XTDs

  • Fast valve in XTD9 still has issues with noise and will probably need to remain disabled

FXE

  • Interlock for loop 1 was deployed. Still need to do loop 2. Work per loop requires ca. 3-4 h.

SPB

  • Firmware for the AGIPD hv power supply was updated. The spikes during ramping are gone
  • Next items to get going are the SMARAGD motors
  • Loop 7 needs to be brought back. Crate 51 has been fixed.
  • Work on in vacuum interlock in SPB will need to be carefully timed and coordinated after finishing FXE. Due to impending beam probably not before next week