SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 552
Entry time: 22 Aug 2018, 10:08
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SASE3 general
- Interlock definitions for the tunnels: today a meeting with AE/HSInn/CAS will take place at 14:00 to continue the discussion.PGessler pointed out that one has to make sure to implement a concept which is also OK with D3 to avoid wasting time. The common understanding is that HSinn is the interface to D3 at this moment.
SQS
- Deployment of new interlock definitions needed. Definitions being prepared by SQS. Ongoing.
- Loop 6 will be needed in the next days. A couple of cables for these 2 crates are missing. Should be there in a couple of days. SQS wants the loop running anyway.
SCS
- Due to absence of beam, SCS is now focussing on the end to end test of components considered priority 2 so far.
- Elmo motors of the FFT chamber need to be rewired. AE on it.
AE
- Loop 3 SQS ready to be updated.
XPD
- Exit slit imager for SQS repaired yesterday.
- Procedure to correctly operate the XGM in XTD2 has been posted by J. Gruenert in the Photon commissioning team logbook.
CAS
- XTD6 technical commissioning will be focussed of the MID CRL this week. Some tests were already done, others have to be done when L.Batchelor is back. AE support (N.Jardon) is requested.
- For CAS top priorities are: SASE1 and SASE3 operation/readiness
|