Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
SPB
SQS
XO
ToBeMigrated2XWiki
ToBeMigrated2GitlabPages
ToBeMigratedByGroup
Migrated2Zulip
Archived2PDF
not2MigrateOrArchive
SCS
SXP Migrated2Zulip
Photon Commissioning Team
XRO
DOC
HED Migrated2Zulip
WP74
MID
PSPO_XO
XO_Operation
SQS Migrated2Zulip
FXE Migrated2Zulip
DET
Sample Environment
SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness
Technical integration and coordination
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
513
Entry time:
18 Apr 2018, 13:43
Author:
Adriano Violante
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 13:00
SPB
Karabo has been deployed without major problems!
Now PLCs update follows. Sample chamber's PLC will be updated next week due to ongoing tests until monday.
It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests.
During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE
AE
Timing servers update - this Thurdsay, starting at 14:00 for 1 hour the trigger and train id signals will be not available.
Updating PLCs for MPS in the tunnels
ITDM
Network stability problems in SASE3 are understood and a workaroung is being implemented.
General
Closing time of the tunnels on monday still not clear. To be clarified by PSPO.