SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 513
Entry time: 18 Apr 2018, 13:43
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
SPB
- Karabo has been deployed without major problems!
- Now PLCs update follows. Sample chamber's PLC will be updated next week due to ongoing tests until monday.
- It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests.
- During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE
AE
- Timing servers update - this Thurdsay, starting at 14:00 for 1 hour the trigger and train id signals will be not available.
- Updating PLCs for MPS in the tunnels
ITDM
- Network stability problems in SASE3 are understood and a workaroung is being implemented.
General
Closing time of the tunnels on monday still not clear. To be clarified by PSPO. |