Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 326     Entry time: 12 Jul 2017, 10:45
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 meeting 

XTDs

  • Mechanical operation of KMONO is prepared. Work is now ongoing on optimizing the scenes in KARABO
  • Data from the SR imager that is needed for scanning the undulator gaps needs to be available in DOOCS. This is prepared.
  • Once the machine can provide beam, one hour for KMONO first commissioning has already been agreed

SPB

  • Test of the Emergency Power Off should take place this afternoon. PLCs will be shut down and hence parameters have to be put badk
  • N. Jardon will put as much information as she can into the firmware do reduce the work of putting back the parameters
  • However, in FXE it was found that the Emergency Off buttons only act on the interlock and not on the electrical systems. The situation in SPB is probably similar
  • Work is ongoing on technical commissioning but there are still key components physically missing (e.g. CSS and Sample Environment)
  • Vacuum interlock is not yet implemented as it is still waiting for a number of components  in loops 12 and 5

FXE

  • JJ XRay worked last week and now the vacuum has to be re-established. Pump down should start soon but there was still one leak.
  • Vacuum interlock definition is ready and it will be implemented by AE today
  • LPD was installed. Currently 2 out of 4 super modules are installed. The other two should come early next week

DAQ

  • Cabling and preparations are ongoing
  • Tests should start early next week

AE

  • Currently working on changes in loop 12 for SPB

CAS

  • Currently working on bug fixes. Some of these bugs are probably responsible for the system not updating vacuum info for 30 minutes
  • Deployment should happen this or next week
  • There appears to be some confusion/communication issue as to what version of KARABO is installed where.
  • It needs to be ensured that the startup of the next photon commissioning period goes smoothly