Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 326
Entry time: 12 Jul 2017, 10:45
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
XTDs
- Mechanical operation of KMONO is prepared. Work is now ongoing on optimizing the scenes in KARABO
- Data from the SR imager that is needed for scanning the undulator gaps needs to be available in DOOCS. This is prepared.
- Once the machine can provide beam, one hour for KMONO first commissioning has already been agreed
SPB
- Test of the Emergency Power Off should take place this afternoon. PLCs will be shut down and hence parameters have to be put badk
- N. Jardon will put as much information as she can into the firmware do reduce the work of putting back the parameters
- However, in FXE it was found that the Emergency Off buttons only act on the interlock and not on the electrical systems. The situation in SPB is probably similar
- Work is ongoing on technical commissioning but there are still key components physically missing (e.g. CSS and Sample Environment)
- Vacuum interlock is not yet implemented as it is still waiting for a number of components in loops 12 and 5
FXE
- JJ XRay worked last week and now the vacuum has to be re-established. Pump down should start soon but there was still one leak.
- Vacuum interlock definition is ready and it will be implemented by AE today
- LPD was installed. Currently 2 out of 4 super modules are installed. The other two should come early next week
DAQ
- Cabling and preparations are ongoing
- Tests should start early next week
AE
- Currently working on changes in loop 12 for SPB
CAS
- Currently working on bug fixes. Some of these bugs are probably responsible for the system not updating vacuum info for 30 minutes
- Deployment should happen this or next week
- There appears to be some confusion/communication issue as to what version of KARABO is installed where.
- It needs to be ensured that the startup of the next photon commissioning period goes smoothly
|