Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 183     Entry time: 27 Apr 2017, 15:11
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 meeting 

 XTDs Info:

Tunnel XTD2/4 will be accessible today until 1500. Dosimeter and General radiation training required. 

XTD10 will be closed starting this afternoon

Vacuum:

 

  • DPS with interlocks was tested successfully yesterday evening but...
  • ... Complete failure of gas sections in both XTD and XTD9 some time tonight. Valves were closed and turbo pumps were off. Reason is still being investigated
  •  
  • Systematic tests of ion pumps in XTD9 done for 3 vacuum sections. Currently only the pumps are tested. Tests of the interlock will follow
     

Karabo:

  • The problem with the GUI server has unfortunately not re-occured. Hence it can currently not be debugged.
  • Second GUI server is available for fall back
  • Remote reset of TP controllers has been implemented and will be deployed in the next release

PLC

  • A problem was found in the MC2 library affecting the ELMO controller.  This only affected the systems deployed in the tunnel. 
  • The non-linear behaviour of the PBLM motors was reproduced independently of PLC and KARABO. Suggestion: Could this happen when the motor has to work against vacuum pressure? Evidence: It does not occur in the lab (no vacuum!)
  • A video session with the manufacturer is schedule for next week to look at the problem

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
  • ASilenzi will discuss offilen with Natalia the acceptance test definition for PBLM
  • List of errors and relative solution concerning ELMO absolute encoder implementation being worked out by AE/CAS

EPS

  • Logic of EPS was agreed between AE and H. Sinn:
    • Currently only covers devices up to XS3
    • Vacuum ok requires all valves to be out of the way
    • Any screen down  forces single bunch mode
    • All imagers in safe position allows full beam mode
  • Meeting next week @ DESY to discuss technical details with MPS group

SPB Tunnel components

  • Renishaw encoder can be read out reliably after fix for error signal line
  • SPB would like to work on the pulse picker next and is waiting for it to be integrated

FXE

  • FXE guys would like to help with tests of Hard X-Ray Mono 

Tasks for today:

  • Perform various maintenance tasks in XTD2, e. g. integrate CRLs, exchange photo tubes, exchange gases
  • Investigate why gas sections switched off yesterday
  • Continue test of vacuum components in XTD9

 