Message ID: 546     Entry time: 16 Jul 2018, 14:18
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Mirrors installed. Lid closed.  Las vacuum connection will be closed today. Then the electronics can be connected. 
  • Mock up pulse picker system ready
  • Some crates in the tunnels will be switched on today after updates of the interlock definitions to be ready for photons.
  • Train on demand technique is currently being discussed by FXE with DESY. SPB should be also involved.

SCS

  • Some problems occur during the test of the PLCs, plus after firmware update new problems showed up. Patrick Gessler will organize a meeting with SCS and Bernard to improve the communication and identify the error sources.

SQS

  • Tests ongoing. No relevant issues so far.

ITDM

  • Working on new proposals format.

CAS

  • XTD 6 open until the end of September.
  • This week due to lack of resources by AE only the last slit and one PBLM will be commissioned. The rest will be done next week.