Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 485     Entry time: 07 Mar 2018, 11:14
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB:

  • Monday morning Karabo failed. It was not possible to operate anything. Aftrer restart it took 2 hrs. to have the tunnel loop and Lopp 5 again operable . Other issues connected to that. CAS is on it.
  • AGIPD can be operated with some workaroung concerning the control system. No final fix available yet.
  • CSS can be operated locally.
  • Coordinated motion test probably on 14.03.

FXE:

  • IPM/XGM correlation data process ongoing. 
  • DAQ worked reliably
  • Scan tool operational for almost every component. Data storage works. Test ongoing.
  • PG points aout that no MPS definitions were given and no MPS is available for FXE yet. To be checked.

SQS

 

  • Corrdination of installations in the hutch with the TUV tests for Rad. Interlock needed.

 

SCS

 

  • Nothing ton report

ITDM:

  • FXE LPD slow data separation will be done today after the meeting
  • Some devices are setting the train id as "0". CAS is informed.

SASE3

MCP HV - Crate restarted. Now ok. There was a misconfiguration of Power/Karabo settings. This meeds to be avoided increasing the communication between people performin operations on the XPD components and the technical support groups.

AE

  • uTCA crate in SASE2 for timing being prepared, as well as PLC for VAC loop
  • Replacement of a uTCA crate in the balcony room for SASE2 needed