SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 485
Entry time: 07 Mar 2018, 11:14
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SPB:
- Monday morning Karabo failed. It was not possible to operate anything. Aftrer restart it took 2 hrs. to have the tunnel loop and Lopp 5 again operable . Other issues connected to that. CAS is on it.
- AGIPD can be operated with some workaroung concerning the control system. No final fix available yet.
- CSS can be operated locally.
- Coordinated motion test probably on 14.03.
FXE:
- IPM/XGM correlation data process ongoing.
- DAQ worked reliably
- Scan tool operational for almost every component. Data storage works. Test ongoing.
- PG points aout that no MPS definitions were given and no MPS is available for FXE yet. To be checked.
SQS
- Corrdination of installations in the hutch with the TUV tests for Rad. Interlock needed.
SCS
ITDM:
- FXE LPD slow data separation will be done today after the meeting
- Some devices are setting the train id as "0". CAS is informed.
SASE3
MCP HV - Crate restarted. Now ok. There was a misconfiguration of Power/Karabo settings. This meeds to be avoided increasing the communication between people performin operations on the XPD components and the technical support groups.
AE
- uTCA crate in SASE2 for timing being prepared, as well as PLC for VAC loop
- Replacement of a uTCA crate in the balcony room for SASE2 needed
|