SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 168     Entry time: 25 Apr 2017, 13:49
Author: Raśl Villanueva-Guerrero 
Location: XTD9 
Severity: Information 
Subject: XTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - Not Working (yet) 

 After some minor issues, the first test has been done today and the interlock wasn´t triggered despite the conditions were met (also visible in Karabo).

 

This requires intervention and revision from AE

 

The next try-out should be done as soon as possible during this week.

 

Regards.

 

Raúl, Benoit and Valerii

 

 

 