SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 589
Entry time: 07 Jan 2019, 09:55
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SPB/SFX
- CRLs will be brought in the SPB lab in XHQ. The vacuum group is installing the replacement pipe.
- SFX cabling starting today.
FXE
SQS
SCS
MID
HED
OPT Lasers
XRO
- M2 in SASE3 is being replaced and the mechanics need to be re calibrated.
XPD
- FEL imager screen in XTD2 has been replaced.
- FEL imager screen in XTD10 will be replaced today or tomorrow.
VAC
AE
- SASE2 VAC loop has been updated.
- The VAC group requested an update of all the motion loops in the tunnel due to some problems with the encoder readout. In principle this could be done next week, but AE will meet with VAC and OPT to discuss the details before.
- MID/HED monos being commissioned.
EET
ITDM
- There was a network update last week
- This Wed/Thu the Maxwell clusters will be updated. No offline computing possible.
- Most of the activities planned for the WS have been done.
- Installation of new storage for SASE1 will be done in thenext days.
- OS in the PCs in the control rooms need to be updated. This will be coordinated with the intruments.
DET
CAS
- CY is now back working on the Mpots (SASE2 and 3). Changes have been implemented. SQS to perform tests. Documentation has also been updated and will be circulated probably next week.
- Karabo training has been organized. The agenda will be circulated soon.
- SPB Karabo upgrade has to be agreed with SPB/SFX.
AoB
- Fridays OP/Readiness meetying moved to 9.30 from now on.
|