  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 575     Entry time: 05 Nov 2018, 12:25
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

FXE

SQS

  • Crates for Loop12 have been installed. Loop will probably run by today or tomorrow.
  • Loop 2 and 3 need to be updated because of interlock definitions.
  • Issue with  valves behavior in Loop 3 and 5. AE will check.
  • Encoder w/o 5 V. BB checks.
  • Pfeiffer Motor valve issue will be fixed by next week.

SCS

 

MID

  • AGIPD will move in the hutch this week. Preparation ongoing.
  • Loop11 will be ready early next week

HED

XPD

  • Several tests planned for the end of the week, including the feedback device by CAS. PRCs will be made aware of the activities in the tunnels.

VAC

AE

  • PPL update in SASE1 today.
  • Update of the Loop 5 (AGIPD) tomorrow

ITDM

CAS

  • Issues in the calibration pipeline will be coordinated with the relevant groups (DET, AE) before and during the next chapter's meeting.

AoB

 