SASE1 Status and SASE3 Readiness
 | 
|   Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  | 
Not logged in | 
  | 
   | 
| 
Message ID: 575
    Entry time: 05 Nov 2018, 12:25
 |  
| Author: | 
Adriano Violante  | 
 | Location: | 
General  | 
 | Severity: | 
Information  | 
 | Subject: | 
Status report after dispatch meeting 09.30  | 
 
  |  
 
 | 
SPB 
FXE 
SQS 
	- Crates for Loop12 have been installed. Loop will probably run by today or tomorrow.
 
	- Loop 2 and 3 need to be updated because of interlock definitions.
 
	- Issue with  valves behavior in Loop 3 and 5. AE will check.
 
	- Encoder w/o 5 V. BB checks.
 
	- Pfeiffer Motor valve issue will be fixed by next week.
 
 
SCS 
  
MID 
	- AGIPD will move in the hutch this week. Preparation ongoing.
 
	- Loop11 will be ready early next week
 
 
HED 
XPD 
	- Several tests planned for the end of the week, including the feedback device by CAS. PRCs will be made aware of the activities in the tunnels.
 
 
VAC 
AE 
	- PPL update in SASE1 today.
 
	- Update of the Loop 5 (AGIPD) tomorrow
 
 
ITDM 
CAS 
	- Issues in the calibration pipeline will be coordinated with the relevant groups (DET, AE) before and during the next chapter's meeting.
 
 
AoB 
   |