SASE1 Status and SASE3 Readiness
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
503
Entry time:
11 Apr 2018, 13:48
Author:
Adriano Violante
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 13:00
SPB
Detector z motion would be needed. AE checks the status of the crate. still pending
MIrrors installation ongoing. NO ACCESS to D.02!!!!
Laser Interlock change of logic by K.Witt will be done on monday at 9:00
Karabo update installation dates being agreed with CAS. Probably early next week.