Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 596     Entry time: 25 Jan 2019, 10:07
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Report after dispatch meeting 09.00 

SPB/SFX

  • Trigger for Jungfrau detector is needed. 
  • Commissioning of the instrument should start next week
  • Loop priorities for the donwstream components have been set with AE.

FXE

SQS

  • VAC interlock test will be done during next days after update of the loop.
  • Loop 4 has to be updated following some HW changes. Should run by next week since is needed for the preparation of the users run.
  • Digitizers crate is being tested by AE and CAS and will be installed/usable by the middle of next week.
  • Burst trigger - status and requirements will be discussed with BFernandes after this meeting.
  • MPOT test CY/TB Today at 13:30

SCS

MID

HED

  • Preparation of Hi res mono has been completed last week
  • OPT hutch CRL commissioning ongoing. ATT will follow (needed missing crate will be installed next week)
  • Chamber motion for the monochromator has to be checked 

 

OPT Lasers

XRO

  • Loops update in thetunnels have been completed. the MOV1 in SASE3 included also some PBLMs ==> XRD should check whether everything is fine afte the update.

XPD

VAC

  • Tunnels are ready for beam.

AE

  • EXAPOD in SPB can be tested.
  • HED need PPU in XTD6. To be re-checked.
  • The timing software needs to be updated. BFernandes circulated a mail with proposed date: Next monday at 14:00. In case of different suggestion, please contact Bruno. CAS suggests to keep the proposed date.

ITDM

ET

CAS

  • Data logger schould be working for every component now. ==> Meeting later with VAC and Laser group to define the use case and start a new optimization project.
  • VAC of HED Opt tests are ongoing (CY) before pumping down.
  • For the debug of gauges control is possible that a ZZ access will be requested. (CY)

AoB

  • Tunnel access schedule will be updated by HSinn after the Operation meeting with the latest information.