The SASE3 tunnel XTD10 was searched by Janni and her team and interlocked about one hour ago.
It is now almost ready for first lasing in SASE3:
- The vacuum is completely connected and closed from V0 all the way to the end
- All valves, pumps and gauges are included in the PLC loop and can be controlled from Karabo
- The gas attenuator section was completely tested and is also under PLC control. The turbos are isolated from the rest of the vacuum and put into a safe state
- All three DPS's are operational, tested and included
- All imagers are operational
- The XGM vacuum is part of the general vacuum and controlled and monitored from KARABO
- The interlocks of the DPSs were succesfully tested
In order to allow beam, it is estimated that one access with approximately 8h would be needed to sort out some remaining smaller issues
I would like to thank the entire team from Vacuum, Optics, Diagnostics, AE and CAS for the big effort and in particular C. Youngman for coordinating. |