Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 202     Entry time: 03 May 2017, 13:29
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: *IMPORTANT* Change of plans re Access tomorrow 
Due the recent results from XFEL, the urgent maintenance is shiftet from Thursday 4th to Friday 
5th. On Thursday, there will be operation till 14:00, after 14:00 the machine will be 
switched to standby. All the work planned will shift accordingly by one day. No ZZ before 
Thursday 14:00. 
 
The machine will be shut down Friday moring 7:00. 
 
Interlock situation: The machine will stay in interlock, only the access to XTL from OSDORF will 
be brocken.  
 
XTL: Access from Osdorf 
- activation measurement XS1 XTL/rear part by D3 
- Leak search and repair in the TLD beamline by MVS 
- A20 work by MHF-p (Exchange of filament heating, work on phase shifter) 
- CS8 RF measurement on load (MHF-p) 
- Repair of wire scanner relais 
 
XTL: Access from Bahrenfeld 
- Exchange of filter in the BCM monitors by MKS 
- Repair of DCCT of a B2D quad 
- Change of AMC board in A8 by MSK 
 
XTD2: 
- ZZ for repair of a BPM system 
XTD10:  
ZZ for Photon Beamline Work 
 
 
All further work has to be agreed by the run or machine coordination. 
 
ELOG V3.1.4-7c3fd00