Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 299
Entry time: 23 Jun 2017, 11:11
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1 Readiness Meeting |
|
|
General
- A low intensity beam is being put into the SASE1 intrument hutches in this order: SPB Optics, FXE Instrument, SPB Instrument
- No special precautions outside the hutches are needed due to the low intensity.
- The work will most likely not finish today. If necessary ti will continue next week Monday
- From now on, access to the SPB Optics, SPB Instrument and FXE Instrument hutches requires these three safety trainings
- General Safety (AllgSi)
- XFEL Safety (SiXfel)
- General Radiation Safety (StraSchu)
- Check with SRP if you are not sure about yout status
XTDs
- W. Freund and the AE colleagues successfully tested their firmware on the the KMONO in HERA-s. This will be integrated in the motion loop and a controlled access will be requested on Tuesday to try this out in XTD2
FXE, SPB:
- Working in the hall to bring the beam into the hutches
Laser:
- 90% of the hardware is installed on the tables
- Humidity in the laser hutch still varies wildly, even after the humidity in XHEXP1 is below 60%
- Humidity variations translate into a pointing instability of the seed laser which cannot go into the amplifier
- There is a discrepancy between KARABO names and motor terminal names that needs to be cleaned up
Detectors
- Interlock tests on AGIPD were successfull
- The train builder is integrated
- LPD is about to finish the tests in the X-ray chamber
- Afterward the KARABO version needs to be updated
- Transport ot FXE is scheduled for week 27
Electronics:
- Getting SPB and FXE ready for today's beam exercise required quite some short term effort
- Mahadi had to get the cameras ready
- Bruno had to set up the trigger timing
- Implementation of the interlock conditions were delayed for the exercise of bringing the beam in. This should happen immediately afterwards together with the connection to the MPS system which is currently not present
- The remaining problems with vacuum in SPB and FXE were solved (Some had to do with hw problems and wrongly wired controllers)
- Work continues on bringing up more SPB loops. Most recently loop 4 was brought up and the firmware for loop 7 is prepared for tests
- Implementation of the interlock conditions were delayed for the exercise of bringing the beam in. This should happen immediately afterwards
- The work on KMONO delays some of the instrument work
Software:
- CAS is currently working with high priority together with ITDM to get the DAQ system and archiving up
- There was a dedicated SQUAD for this purpose
- The functionality has already been tested successfully on the LPD detector.
- The interface needs work to become usable
- Tests of full scalabiity are still outstanding
- The system needs to be deployed in the real environment
- It is estimated that the remaining work should take ca 3 - 4 weeks
|
|