Message ID: 262     Entry time: 24 May 2017, 10:39
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status after 0930 meeting 

 General:

  • DESY will try to lase again at higher energies during the next days
  • XTD9 will searched an interlocked this afternoon at 1400 as PCT will try to transport photons as far as possible
  • Company Wille has started to work on the radiation interlocks in SASE1. New TÜV date on 20 June and rehearsal on 14 June
  • Instruments should be prepared that on these days

 

XTDs:

  • CAS (A. Parenti) is still working on the instability problem of the SR imager. For the moment the workaround with reduced resolution (mono-8) seems to acceptable
  • One (non-existing) pump needs to be removed from interlock conditions in XTD9. Otherwise interlock blocks one gate valve
  • Filter was taken off the pop-in in XTD2
  • Tests for PBLMs still need to be done in XTD9 when it re-opens next week

FXE:

  • Problems exist with vacuum controls. J. Tolkiehn is currently working on it
  • Firmware of commissioning crate was upgraded
  • Test of Johan Spectrometer was done with test crate
  • CRL test are next

SPB:

  • Still waiting for firmware for loops 1&2. AE is almost ready and will deploy today
  • All cables are ready for Optics hutch
  • AE is currently pushing in the crates

PLC:

  • DESY MPS claims that a cable from the interlock to an AE crate is still missing. 
  • AE got vital information from MPS just a few days ago and is still waiting for info from the laser interlocks

KARABO:

  • CAS is working on a version with bug fixes for stability. Will be deployed when appropriately test and when a break is available
  • X2 timer interface still has issues. A. Sienzi is working on it

ITDM:

  • An update of network switches is needed. This will be scheduled for next week. Details to be discussed during Monday 1500 BKR meeting

 

ELOG V3.1.4-7c3fd00