SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 543     Entry time: 09 Jul 2018, 14:32
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Mirrors installatiostarting now. Preliminary motion tests conducted last friday were successful. Still closed loop for encoders signal has to be implemented. AE will work on that.
  • AGIPD firmware updated. Remaining tests ongoing. New Karabo release will be deployed tomorrow.
  • Peltiers being tested. 

SQS

  • End to end tests procceding. Laser incoupling and NQS chambers being set up.
  • Loop 5 needed for next week.
  • M pot firmware issue is being adreesed by CAS
  • It is not possible to switch the ion pumps on and off remotely using Karabo. AE and CAS to look into that.

 

AE

  • SASE3 exp. Loops preparation ongoing
  • SPB Loop 4 update being prepared
  • SASE3 tunnels interlock definitions are being updated for some diagnostic component
  • SASE2 MID CRLs being tested.

 

CAS

  • SPB 2.2.4.1 Karabo update scheduled for tomorrow morning between 7 and 9.