On monday there was an issue with a detector related PLC due to misconnection of one EtherCAT cable. The issue has been solved and it "just" resulted in 3 of hours delay in the AGIPD calibration activity.
FXE, SCS, SQS, XPD, XRO,ITDM no issues reported
AE related
uTCA in XTD 6 are installed
VAC-Related
Marc Messerchmidt reported abouit an entry in the DESY Logbook about a pump that triggered the interlock in the SASE1 tunnels. According to Nerea this this seems to be related to the old issue already known. VAC group is working on that.
CAS
CYoungman is working on the priority list for the components in SASE2 tunnels. Double checking with HSinn happening soon.
Access for Tue/Wed next week to XTD1 will be requested by CY through HS
Beam is in SPB/FXE this week due to the HERCULES project. |