Message ID: 491     Entry time: 21 Mar 2018, 10:02
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

On monday there was an issue with a detector related PLC due to misconnection of one EtherCAT cable. The issue has been solved and it "just" resulted in 3 of hours delay in  the AGIPD calibration activity.

FXE, SCS, SQS, XPD, XRO,ITDM no issues reported

AE related

uTCA in XTD 6 are installed 

VAC-Related

Marc Messerchmidt reported  abouit an entry in the DESY Logbook about a pump that triggered the interlock in the SASE1 tunnels. According to Nerea this this seems to be related to the old issue already known. VAC group is working on that. 

 CAS

CYoungman is working on the priority list for the components in SASE2 tunnels. Double checking with HSinn happening soon.

Access for Tue/Wed next week to XTD1 will be requested by CY through HS

Beam is in SPB/FXE this week due to the HERCULES project.