Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 583     Entry time: 03 Dec 2018, 11:45
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • pulse arrival time measurements to be done next week.
  • second Gotthard detector small issues being fixed

FXE

SQS

  • Successful experiments during the WE

SCS

  • Z-motion issue for the fast CCD. Has to be checked again with AE today

MID

  • Loop 7 is running
  • This week light is expected on the AGIPD
  • Mono commissioning issue: the pico motors position is not reproducible. ==> motor is now stuck, needs to be replaced.
  • Loop 10 partially needed. To be discussed with AE

HED

XRO

XPD

VAC

AE

  • The synch of the Gotthard detectors with 1 trigger does not work for long trains (synch is lost). Multiple triggers are needed. AE is looking into that involving A. Galler since he is an advanced user of the Gotthard. The solution will then be deployed to all the detectors.

  EET

ITDM

 

CAS

  • Tests with AE/ITDM ongoing. In the new version of Karabo/DAQ the filtering of slow data for device will be included.

AoB