SASE1 Status and SASE3 Readiness
Technical integration and coordination
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
428
Entry time:
04 Dec 2017, 10:56
Author:
Tobias Haas
Location:
General
Severity:
Information
Subject:
Status after 0930 meeting
General:
User operation with good beam conditions over the weekend
One interlock trip in the FXE branch in XTD9. Restored by CAS
Shutdown starts tomorrow at 08:00.
Next dispatch meeting takes place Wednesday at 13:00. A reminder will be sent.
Instruments
SPB:
Started with the actual sample during the night shift
Some DAQ issues
108TB data was recorded
Problems appear to occur between 01:00 and 02:00 and between 13:00 and 14:00
FXE
Running is ok.
Temporal and spatial overlap with optical laser established
Currently taking pump-probe data
People on shift were uncertain about how to recover from interlock trip
Statement from Vacuum: Pumps can restarted/valves open if the respective button in KARABO can be clicked
CAS:
Delay between data taking and "online" analysis in the "Hummingbird" software is about 0.3s
ITDM
On Friday, there was a global network outage affecting the Office Network on the DESY site.
The transponder system in the experiment hall was down
SRP organised a guard at the hall entrance so that the hall had not to be evacuated
The control network (XDAC) was not affected