Message ID: 545     Entry time: 12 Jul 2018, 08:11
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Mirrors being installed. Tests continue. Karabo updated.

AE

  • Works in the tunnels SASE3 and 2 continue
  • Works on the SASE3 experiment preparation continue

General

Works to ensure the redundant power for Racks in SASE3 have to be performed. A suitable date has to be found. PSPO will coordinate that.

 