Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 545     Entry time: 12 Jul 2018, 08:11
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Mirrors being installed. Tests continue. Karabo updated.

AE

  • Works in the tunnels SASE3 and 2 continue
  • Works on the SASE3 experiment preparation continue

General

Works to ensure the redundant power for Racks in SASE3 have to be performed. A suitable date has to be found. PSPO will coordinate that.

 