Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 545     Entry time: 12 Jul 2018, 08:11
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Mirrors being installed. Tests continue. Karabo updated.

AE

  • Works in the tunnels SASE3 and 2 continue
  • Works on the SASE3 experiment preparation continue

General

Works to ensure the redundant power for Racks in SASE3 have to be performed. A suitable date has to be found. PSPO will coordinate that.

 

ELOG V3.1.4-7c3fd00