SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 229
Entry time: 12 May 2017, 13:33
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1 Readiness Meeting |
|
|
Focus of meeting is on SASE1 Instruments, Laser and Detectors
SPB (B. Weinhausen)
- All motors in the SPB tunnel loop have been commissioned except for one TECHNOSOFT motor where the updated driver was not yet available
- Comment by P. Gessler:
- The updated MC2 lib was deployed yesterday evening. Testing should be possible now
- The second camera of the screen broke. Concern exists over possible overvoltage in the power that comes directly from the PLC
- All encoders are working
- The vacuum in the Optics hutch is closed
- Info by A. Violante:
- All cabling in D02/D03 is done
- There are a few damaged connectors that prevent pushing in the modules. This should be fixed on Monday
- Pins are swapped in one connector. Will be fixed locally
- Comment by P. Gessler:
- This week AE was busy with AGIPD and tunnels
- Next week resources should be available to support start of commissioning loop 1
FXE (A. Galler)
- E2E tests are progressing
- A recent update of the Beckhoff firmware generated new problems with encoders
- Info from T. Korsch:
- The vacuum in the hutch is closed and has reached 5e-7 mb
- There is a minor leak in one of the bellows
- Compressed air is working to operate the gate valves
- Vacuum gauges can be read out remotely
- Attention should be paid to being able to read out detectors, e. g. diodes
Laser (D. Kane/M. Lederer)
- Slides were provided in INDICO with a detailed account of the status. Only Key points are summarised here:
- Hutch infrastructure is working in general and temperature stability is ok but laser group is lacking access to controlling the parameters, humidity is oscillating and smoke detectors are not connected
- Pre-assembly of PP laser is 75% done
- Beam delivery to instruments is on the list now
- Synchronisation with optical system might not be available before October
- Control are generally working and software has improved a lot but some stages cannot be controlled and Karabo appears still to have some resource leaks
Detectors (M. Kuster)
- LPD is in E2E tests and AGIPD is still being integrated into the XFEL environment
- This week it was possible to run the DAQ chain on LPD for the first time
- All tests on LPD including data taking in the X-Ray chamber in HERA-S should be done by end June
- Situation with AGIPD is more difficult as basic integration is still not complete
Discussion
- Follow up on progress with instruments, laser and detectors will continue in S1R meeting from now on
- The S1R dispatch meeting takes place on Mondays 09:00 in BKR and on Wednesday 09:30 in XHQ
- Groups that require help from AE and CAS and that need to coordinate with other activities should attend
|
|
|