Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 351     Entry time: 31 Jul 2017, 11:58
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status after 9.30 dispatch Meeting 

General

  • SRP was not able to measure any radiation even inside D.09 and D.02. This Thursday the radiation test in D.05 (FXE) will be performed. 

  • Tomorrow XTD9 open 7:00 ==>14:00

FXE

  • Gotthard detectors to be tested in Karabo

SPB

  • Problem with Smaract motors has been identified. Loop to be updated. 

  • Cameras trigger for the sample environment is now working. Software issues.  CAS is addressing that. 

  • Vacuum interlock for Loop 5 (AGIPD) is being implemented. There will be a meeting soon (today?) with AE to check the interlock definitions for AGIPD and continue work on this loop.

  • Focus characterization with CRLs ongoing. Beam size reached: <10 um

 

  • Tunnels

  • Fast valve fake triggering has not been reported in the last week end. 

  • In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.

  • Some problems with the cameras that stopped working have been reported by A. Koch. That could be just a matter of restarting the GUI. To be checked.

AE

  • FXE Interlock definitions have been changed and this reflects in the update of loop 1 and 2. Ongoing.

  • Working on Alio Stages integration for Mono in the tunnel. To start this week. 

  • SPB Loop 12 – Smaract motors and ELMO controllers implementation ongoing

  • SPB Loop 5 is up including the AGIPD related systems. AGIPD interlock will be added once low level tests done

  • SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. SPB wants to leave it and rather swap module positions and hand in a change request.

  • Cables for interface to Person Interlock laid. Connections to the MPS system to be done this week.

  • DET

  • LPD – Time server was set up. Images collected from 1 quadrant. Firmware upgrade for the other quadrants ongoing. 

  • AGIPD – Detector being tested in Hera south. KWrona will start the tests of DAQ in Hera today or tomorrow.

     

    CAS

  • 2.1.13 Karabo version update is being agreed with the interested parties. It takes approx. 1-3 hrs. 

ELOG V3.1.4-7c3fd00