Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 349     Entry time: 28 Jul 2017, 11:50
Author: Frederike Wittmaack 
Location: General 
Severity: Information 
Subject: Status and plans after SASE 1/3 Readiness Meeting 

General

  • The radiation test in SASE1 could not take place yesterday since the machine was not able to deliver proper light intensity with 30 bunches. Another tentative is happening now.

  • Instrument commissioning during the weekend

  • Monday - Wednesday next week will be machine development time. XTD 9 will be accessible on request. Please contact M. Dommach. XTD 10 is foreseen to be close.

     

    SPB

  • After tests Smaragd motors are not working. Under investigation with AE/CAS

  • Cameras trigger for the sample environment is not working. AE has been made aware of that during the meeting. Ongoing checks.

  • Vacuum interlock for Loop 5 (AGIPD) is being implemented. This has to be done before the detector installation (foreseen beginning of August).

  • Freezing and delays of the GUI are being experienced. CAS ticket has been sent. This has to be addressed as soon as possible in view of the instrument commissioning time during the week end.

     

    Tunnels

  • Fast valve fake triggering has not been solved. After tests the suspect was on the controller side. Controller has been replaced but the issue has not been completely fixed. Investigation ongoing. Valves are ACTIVE regardless.

  • In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.

  • XTD10 – progress in the last 2 days have been achieved concerning closing of vacuum gaps and leaks testing

  • XTD6 – Vacuum connections ongoing.

     

    AE

  • FXE Interlock deployed and under tests.

  • Working on Alio Stages integration for Mono in the tunnel. The goal is to have it ready by the end of August.

  • SPB Loop 12 – Smaragd motors and ELMO controllers implementation ongoing

  • SPB Loop 5 is up including the AGIPD related systems. AGIPD interlock will be added once low level tests done

  • SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. SPB wants to leave it and rather swap module positions and hand in a change request.

  • Cables for interface to Person Interlock laid. Connections to the MPS system to be done next week.

  • SASE3 Tunnel - Work started on PLC projects. There is the need for accurate schematics and a list of priorities in order to plan and prepare the shutdown week.

  • SASE3 Instruments – AE will start the installation of components ion the racks soon (Mid Aug. after network cables are finished in the PLC related racks).

  • General remark  - Do not leave cables in tunnels disconnected after having worked!

     

    DET

  • LPD – Trigger problems solved. DAQ tests to continue

  • AGIPD – Detector being tested in Hera south. As soon as the important issues concerning DAQ have been solved in Hera south (time allocated next week for that). The decision to move it to the SPB hutch can be taken. Schedule may be slightly affected, depending of the test results in HERA.

     

    CAS

  • 2.1.13 Karabo version has been presented yesterday

  • Scan tool measurement presentation today at the Mock-up control room

 

Next week NO SASE1/3 Readiness meeting!

ELOG V3.1.4-7c3fd00