SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 55     Entry time: 28 Feb 2017, 11:38
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Reminder: Stable operation and development periods 

One word of clarification:

The discussion last Friday left some people uncertain over how to define stable operation and development periods. Hence I had a discussion with Nerea and Alessandro and agreed on the following:

PLC development: Tuesday - Thursday

Stable operation with Karabo: Friday - Monday

Handover period is Thursday afternoon between AE and CAS 

 