Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 593     Entry time: 18 Jan 2019, 11:05
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Report after dispatch meeting 09.00 

SPB/SFX

  • The interlock definitions in the tunnel were updated. They have to be tested.

FXE

SQS

  • Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). Happening today. After completion CAS and AE support is needed to switch the systems back on. ==> Completed. No issues.
  • AQS chamber has been removed. The reaction microscope is now being installed.
  • New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. 

SCS

MID

HED

OPT Lasers

XRO

​​XPD

VAC

  • Mono loop in SASE 3 has to bee updated (22nd). Agreed with involved parties. 
  • MOV2 Loop SASE2 also needs to be updated. Agreed with involved parties.

AE

  • AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. This task was not included in the shutdown list and therefore has not been planned. The issue needs to be reported in the operation meeting since a reshuffle of priorities and relative decisions are eventually needed.
  • CRLs for SPB will be controllable at the end of March/ beg. April as agreed with the instrument people. 

EET

ITDM

DET

CAS

  • It is pointed out that the CAS policy is not to implement changes in the software on Friday in order to guarantee the smooth operation of components during the week end. This should be also reported in the Operation meeting.

AoB

  • 22/23 January Fa. LIEN will fix the sliding doors in the SASE3 hutches.