Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 593
Entry time: 18 Jan 2019, 11:05
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Report after dispatch meeting 09.00 |
|
|
SPB/SFX
- The interlock definitions in the tunnel were updated. They have to be tested.
FXE
SQS
- Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). Happening today. After completion CAS and AE support is needed to switch the systems back on. ==> Completed. No issues.
- AQS chamber has been removed. The reaction microscope is now being installed.
- New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday.
SCS
MID
HED
OPT Lasers
XRO
XPD
VAC
- Mono loop in SASE 3 has to bee updated (22nd). Agreed with involved parties.
- MOV2 Loop SASE2 also needs to be updated. Agreed with involved parties.
AE
- AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. This task was not included in the shutdown list and therefore has not been planned. The issue needs to be reported in the operation meeting since a reshuffle of priorities and relative decisions are eventually needed.
- CRLs for SPB will be controllable at the end of March/ beg. April as agreed with the instrument people.
EET
ITDM
DET
CAS
- It is pointed out that the CAS policy is not to implement changes in the software on Friday in order to guarantee the smooth operation of components during the week end. This should be also reported in the Operation meeting.
AoB
- 22/23 January Fa. LIEN will fix the sliding doors in the SASE3 hutches.
|