Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 481     Entry time: 28 Feb 2018, 10:55
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB:

  • Ion pumps running in the Mirror chamber. Vacuum level OK to run.
  • D.02 is now interlocked and is a clean area.
  • Mahadi and Alessandro are setting up a test system for the coupled movement. The test will probably be done between the 2 users periods.
  • 2 hours of parasitic beam can be used today to check the alignment of the CRLs. The CRLs will be then moved out of the beam to allow the FXE radiation tests tomorrow.
  • Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to have the primary limits included. CSS crate to be modified after clarification with AE/EET.
  • Test of the karabo brigde will be performed with users. It is not yet clear exactly when since this needs synchronization with several groups involved (CAS, ITDM, DET). 

FXE:

  • Radiation test tomorrow
  • LPD test measurements in thhe WE
  • Von Hamos spectrometer alignment until monday

ITDM:

  • SASE1 and 3 have the last DAQ update now. Stable in SASE1 so far.
  • Data sources arrangement being worked out. Today a 45 min session is foreseen with SPB.
  • SPB needs slow data acquisition from 2 cameras for users, apart from AGIPD.

 

VAC/Detector/XPD/CAS: nobody attended