Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 188     Entry time: 28 Apr 2017, 13:24
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Small correction to minutes posted just before 

Note that plans for next week (points 2& 3) should refer to XTD9 and *NOT* XTD2

 Plans for next week:

  • Consolidate vacuum in XTD2 so that V0 can be reliably opened when first beam should be transported
  • Finish work in XTD9, in particular PBLMs and instrument components
  • Finish systematic tests of ion pumps in XTD9
  • Deploy fix for Renishaw encoders in firmware
  •  
ELOG V3.1.4-7c3fd00