Message ID: 188     Entry time: 28 Apr 2017, 13:24
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Small correction to minutes posted just before 

Note that plans for next week (points 2& 3) should refer to XTD9 and *NOT* XTD2

 Plans for next week:

  • Consolidate vacuum in XTD2 so that V0 can be reliably opened when first beam should be transported
  • Finish work in XTD9, in particular PBLMs and instrument components
  • Finish systematic tests of ion pumps in XTD9
  • Deploy fix for Renishaw encoders in firmware
  •  