Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 523     Entry time: 09 May 2018, 10:09
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Summary of the dispatch meeting 09.30 

SPB

  • Test on the mirrors peltier showed some issues due to the fact that the test boxes were different from the actual stuff. R.Bean will clarify it with FMB.
  • Loops 12,13 update to be done.
  • Magnetic turbos control: the serial communication has some issues. Being checked with AE and CAS

SQS

  • Loop1 cabled up. Some names haad to be corrected in the firmware. As soon as the export is delivered by EET to AE the formware can be uploaded, Probably today.
  • Upstream turbo pumps running using controlers in the rackrooms but still no PLC control.

SCS

  • Some issue with the movement of the motors found. AE is on it.
  • 1 crate does not have enough power to power up all the terminals. Will be solved today.

AE

  • The valves will be included in the interlock systems (SASE1 issue) - Loop ready to be updated - The MPS has to be disabled before updating the loop to avoid tripping of the beam.
  • FXE loops update started

 

DET

  • Hotfix for AGIPD ready to be deployed. Can start today. Details will be sorted out with SPB.

CAS

  • SASE3 Soft Mono is now technically commissioned. PBLMs next in the line.
  • XTD1 CRLs will be integrated iin the control system in KW 22
  • XTD6 priority on the MID beamline. 

General

It is not clear if and when the experiment in SASE1 could get beam during this week. Has to be checked with the PRC.