SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 588
Entry time: 19 Dec 2018, 13:17
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SPB/SFX
- SFX part1 cabling preparation ongoing (WCBs mounting and labeling). Good progress.
- CRLs will be brought out of XTD9 tomorrow.
- Scaffolding below D.23 has been removed. An official communication that now the area is completely accessible is still lacking.
FXE
SQS
- For the loops 9-13 the HW is ready. CAS projects have to be prepared.
- Some issues with middle layer devices have been notified to CAS (Cyril)
SCS
MID
- Karabo 2.3.2 has been deployed apart from the AGIPD control (waiting for tests by DET group before update).
- CY is now back working on the Mpots (SASE2 and 3)
HED
OPT Lasers
XRO
XPD
VAC
AE
- SASE1 power was back yesterday. SPB and FXE have been brought up again yesterday afternoon. Today morning because of unplanned and badly communicated MPS works the power was cut again ==> additional, unplanned efforts needed.
- Hazem will be OCD during Christmas, only for PLCs.
- No uTCA OCD during Christmas.
EET
ITDM
DET
CAS
- 2.3.2 Deployed in SASE2
- SPB update postponed to January
- SASE1 planned for today
- No OCD until 09.01.
AoB
- Next Disptach meeting on 07.01.2019 at 9:30
|