Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 519     Entry time: 27 Apr 2018, 10:21
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Lasing SASE3 

INFO

As reported by the PRC (J. Gruenert) during the operation meeting this morning, due to the first lasing attempt in SASE2 no lasing of SASE3 is to be expected until the middle of next week.