Subject: Status report after dispatch meeting 09.30 

SPB

  • More interlock updated will take place this morning.

FXE

  • Supporting the diagnostic and optics group for the testing of the beam feedback mechanism. 
  • A.Galler was informed by CAS (Vajid) that a Karabo update was requested to CAS last friday late afternoon. The update was stopped by FXE, but to avoid this in the future communication between the cvarious groups has to be improved.

SQS

  • Beam during the WE. NO issues.
  • Imaging processors are being used for cameras. There are issues with the averaging. CAS is informed.
  • Various loops updates needed. Will be agreed offline with AE.

SCS

MID

  • Loop 11 could be ready by next week. Today the FW export by EET is going to be available to AE.

HED

XPD

 

​​VAC

AE

TDM

CAS

  • Karabo 2.3 is now a release candidate. Testing starts today (2.5 wks internal tests). Info about new features of the 2.3. release are available on the white board in front of the mockup control room.