Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
This is a draft message, edit and submit it to make it permanent  
Message ID: 389     Entry time: 25 Sep 2017, 10:25
Author: Monica Aresté 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1/SASE3 Readiness Meeting 

General

To stablish proper conditions for the beam as it was before. On Wednesday to have the mirrors in the correct configuration and machine back to the old conditions at the end of the week.

SASE 1 Instruments

  • SPB (M. Messerschmidts): 
    • Reported several persistant problems with Karabo that affectd the DAQ and Detector. On Saturday detector falled over and took long time to recover. CAS wokring to fix this issue.
  • FXE:
    •  

Tunnels (M. Dommach):

  • SASE1:
    • Beam shutters closed during FXE shift. It is not clear the reasons why this happened, to investigate.

Electronics (P. Gessler)

  • MPS Interlock tested but not swichted on. SPB agreed to switch on the MPS tomorrow.

ITDM (K. Wrona)

  • FXE was runnig  experiments with problems in DAQ, the experiment this was not reported to ITDM
  • Next experiments require Gotthard & LPD in parallel operation ==> to merge Gotthard & LPD to same run control ITDM needs some time to test, agreed to perform these tests Tuesday and Wednesday this week.

Software

  • FXE:
    • Still daily meetings, prepare LPD & Gotthard
    • Working on GreatEyes, too
  • SPB
    • Configure slow-data cameras
    • Laser project is running in CAS
  • SASE3:
    • C. Youngman is the CAS-responsible, should collect requirements to compile master equipment list for SASE3 ==> to be compared against MEL SASE1 to identify additional work required.
  • SASE1:
    • Loops & Karabo will be updated together.

 