SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 463
Entry time: 29 Jan 2018, 14:51
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
SPB/SFX:
- Problems with data loggers ==> no statements about the past.
- Loop 5 upgraded
- Alle the other Loops are not at the 100% of their potential but sufficient for the users.
- Test on nkb mirror movement to be done.
XPO
- In SASE3, 4 cameras have trigger problems. AE is working on that.
- In SASE3, 4 cameras have accessibility problems. ITDM is working on that.
CAS SASE3 (C. Youngman):
- Interlock for VAC, GAT and XGM loops are tested and OK
- The rest is so far as it could go. For details refer to C. Youngman report.
ITDM:
- Broken Linecard replaced .
- Update/switch for the gateway to the control network will happen in one late evening during this week. ITDM will write an entry in the logbook just before.
|