Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 17 Sep 2018, 10:19 
    Reply   Re: Status report after dispatch meeting 09.30, posted by Dennis Goeries on 17 Sep 2018, 14:30 
Message ID: 563     Entry time: 17 Sep 2018, 10:19     Reply to this: 564
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Bug in the AGIPD cooling macro (setpoint resets itself to -59 C)  -  Jola knows about the problem. AS: Macro will be fixed.

  • AGIPD dark calibration: when new darks were injected with calling Steffen's script "xfel-calibrate",  error message "Disk quota exceeded" popped up caused by a GPFS-related issue -> issue was solved. In general the script was not tested (scratch space was used!). One should not release script without ITDM knowing and haveing thested it before. 

FXE

  • Commissioning going on in the last days. Not able to get 14 keV beam for next users experiments. They will stick with 9.3 keV.
  • Karabo stability issue (GUI) reported in the commissionig logbook.

SQS

  • Problem with the digitizers bandwidth has now been solved.
  • Loop 6 running w/o smaract stages.
  • Flow switches issues solved . Rewiring of PLC needed
  • Pfeiifer flow valves ready to be stested this week.
  • Loop assignment changed. Change request handed in. As soon as it is approved it will be clear what loop to bring up next.

SCS

  • Loop 7 is running. Needs to be connected to Karabo.
  • Loop 8 running too.
  • Readiness of loop 1 and 4 ==> Interlock conditions need to be implemented. 
  • It is unclear whether the homing capability has been implemented already and can be used. Discussion ongoing. The use case has to be clarified.
  • Network storage for the control PCs in the control room is requested. Scope definition and discussions with CAS and ITDM will be done offline.

MID

  • Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. This week Slit and ATT will be commissioned. No big issues so far.
  • Loop 4 being prepared by AE. Will be ready next week.

HED

  • Work in tunnel ongoing
  • HRMono- ready to start grouting. Mono will be here next week.

DET

  • FXE/SPB GPUs crash issue  - to be checked with ITDM - ITDM was not contacted.

ITDM

  • DAQ was upgraded to the user friendly version in SASE3. After having discussed with FXE in the meeting, it was decided to install it also in FXE. 
  • DAQ training requested by SQS

CAS

  • Karabo 2.2.5. patch being prepared. Will solve minor bugs and the crash due to empty data files.
  • 28 Mpot update requests were received by CY. Need to be planned and coordinated with H.Santos.

 