Message ID: 283     Entry time: 08 Jun 2017, 08:24
Author: Harald Sinn 
Location: General 
Severity: Information 
Subject: XTD10 and XTD9 tunnel opening and closings 

Dear all, 

according to the DESY logbook XTD10 will be opened today again: See DESY logbook entry:

'due to the cryogenic failure we will open XTD10 from 9am for working.
at XTL and XTD2/4 ZZ is possible for repairs/work.'

I don't know hoe severe the cryo failure is, but otherwise the agreement is that XTD9 will be closed Friday morning around 9am.

(I assume that they may close Friday morning also XTD10 again).

Best regards

Harald  

 