Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 551     Entry time: 20 Aug 2018, 11:46
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SASE3

  • If the bender of the M2 mirror is used the beam can be focused on the shutter and caouse damaged. This is a safety relevant issue that prevents SASE3 from getting beam. Interlock definitions related to the gas attenuator are being discussed to overcome the problem.

SQS

  • Digitizers being set up with ITDM and AE
  • Deployment of new interlock definitions needed. Definitions being prepared by SQS
  • Loop 6 will be needed in the next days. AE reports that it's almost ready and in the next days will be deployed.

SCS

  • Cabling almost 100% done.

AE

  • Problems with ELMO motors reported on 10.08. for the KB optics has been solved.

XPD

  • 2 screens were damagend in SASE3. One has a hole, the other one has surface damages.The imagers should be put in the interlock when multibunch mode is used. For the single bunch mode a warening signal is now appearing in the Karabo scene.

General

  • The next dispatch meeting will take place as usual this Wednesday at 9:30.