Message ID: 498     Entry time: 04 Apr 2018, 17:35
Author: Janusz Szuba 
Location: General 
Severity: Information 
Subject: Control network maintenance 

Tomorrow, 5.04, between 9:30 and 12:00 there will be urgent maintenance of one of the two redundant main switches for the control network. The network connectivity during that time is not guaranteed, but also any major interruptions are not expected. For the two switches in sase1 tunnels with only one uplink, there could be short (~1min) interruption.

Best, 

Janusz