Subject: Accelerator Schedule for the next days 

 Author: Decking

Run Coordinators: W. Decking (93430), D. Sanzone

Tunnels XTIN, XTL, XTD2-4, XTD10 closed
Temporary access to XTL,XTD2-4, XTD10 possible on Wed, 4.5.
Next open access XTIN, XTL, XTD2-4, XTD10 on Wed, 10.05. 08-16

|01/05 Mo M |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz
|01/05 Mo A | Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz
|01/05 Mo N |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz
|02/05 Tu M |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz; establish 6, 8 GeV File
|02/05 Tu A |  Beam operation  to T4D 6 GeV, 1 bunches, 0.5 nC, 1 Hz
|02/05 Tu N |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz
|03/05 We M |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz; study beam optics
|03/05 We A |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz
|03/05 We N |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz 
|04/05 Th M |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz
|04/05 Th A |  No beam operation, tunnels closed
|04/05 Th N |  No beam operation, tunnels closed
|05/05 Fr M |  No beam operation, Acces to TLD for leak search, Temporary access to T2-T4 possible
|05/05 Fr A |  No beam operation, Acces to TLD for leak search, Temporary access to T2-T4 possible
|05/05 Fr N |  No beam operation, tunnels closed
|06/05 Sa M |  No beam operation, tunnels closed
|06/05 Sa A |  No beam operation, tunnels closed
|06/05 Sa N |  No beam operation, tunnels closed
|07/05 Su M |  No beam operation, tunnels closed
|07/05 Su A |  No beam operation, tunnels closed
|07/05 Su N |  No beam operation, tunnels closed
|08/05 Mo M |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 10 Hz
|08/05 Mo A |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 10 Hz
|08/05 Mo N |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 10 Hz