Subject: KW16 Accelerator Plans 

 Author: Decking

Goals:
- Operation with 10 GeV, 500 pC, 5 kA, 30 bunch
- Increase gradient limits in RF stations
- Technical comissioning of north branch 

XTIN closed all week
XTL open till Tue, 11:00
XTD2 open till Tue, 15:00
XTD4 open till Tue, 15:00
XTD9&XTD10 open all week


|17/04 Mo M |  Easter shutdown
|17/04 Mo A |  Easter shutdown
|17/04 Mo N |  Easter shutdown
|18/04 Tu M |  Interlock pre-test CS8, set XTL interlock at 11:00, Injector beam operation
|18/04 Tu A |  A2 calibration after phase shifter change, Beam operation  to TLD 10 GeV, set interlock XTD2-XTD4
|18/04 Tu N |  Beam operation  to TLD 10 GeV, 30 bunches, 0.5 nC
|19/04 We M |  Slice emittance in BC2; Magnet PS test XTD2-XTD4 
|19/04 We A |  BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4 
|19/04 We N |  BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4 
|20/04 Th M |  Collimation set-up; Magnet PS test XTD2-XTD4 
|20/04 Th A |  BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4 
|20/04 Th N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC; Magnet PS test XTD2-XTD4 
|21/04 Fr M |  Collimation set-up with 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|21/04 Fr A |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|21/04 Fr N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|22/04 Sa M |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|22/04 Sa A |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|22/04 Sa N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|23/04 Su M |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|23/04 Su A |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|23/04 Su N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|24/04 Mo M |  Beam set-up 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo A |  Beam operation  to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo N |  Beam operation  to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz