Author: Decking
Goals:
- Operation with 10 GeV, 500 pC, 5 kA, 30 bunch
- Increase gradient limits in RF stations
- Technical comissioning of north branch
XTIN closed all week
XTL open till Tue, 11:00
XTD2 open till Tue, 15:00
XTD4 open till Tue, 15:00
XTD9&XTD10 open all week
|17/04 Mo M | Easter shutdown
|17/04 Mo A | Easter shutdown
|17/04 Mo N | Easter shutdown
|18/04 Tu M | Interlock pre-test CS8, set XTL interlock at 11:00, Injector beam operation
|18/04 Tu A | A2 calibration after phase shifter change, Beam operation to TLD 10 GeV, set interlock XTD2-XTD4
|18/04 Tu N | Beam operation to TLD 10 GeV, 30 bunches, 0.5 nC
|19/04 We M | Slice emittance in BC2; Magnet PS test XTD2-XTD4
|19/04 We A | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|19/04 We N | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|20/04 Th M | Collimation set-up; Magnet PS test XTD2-XTD4
|20/04 Th A | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|20/04 Th N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC; Magnet PS test XTD2-XTD4
|21/04 Fr M | Collimation set-up with 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|21/04 Fr A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|21/04 Fr N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa M | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su M | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|24/04 Mo M | Beam set-up 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo A | Beam operation to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo N | Beam operation to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz |