PSPO:
- M. Areste presented a report about the progress so far achieved in the shutdown (see Indico for details).
- Most tasks are ongoing, on schedule.
- Few still have to be scheduled, mostly because support groups wait for feedback.
- C. Youngman does detailed coordination of SASE3tasks.Will organize meeting on Tuesday 9:30 for SASE3 tunnel only
- We will review the progress again in Mid-January!
SPB (M. Sikorski):
- AGIPD was tested.
- Roll back to crystallography configuration is ongoing.
FXE: No one attended.
Vacuum (M. Dommach):
- 1st mirror M1 in SASE3 installed, chamber closed, pumped down & leak tested
- Preparations for 2nd mirror in SASE3 installation ongoing, to be installed next week.
- MCP taken out of SASE3, put in parking position and pumped down again.
- Grating chamber from FXE was installed by JJ X-ray, is to be pumped in CW 51.
- SASE2 XS2 beam pipe behind shutter and lead wall installed, ready for TÜV inspection next week.
Diagnostics (A. Koch):
- XGM in XTD1 is almost cabled, more cabling was done in XTD10.
- Gas supply system in XTD1+6 was worked on.
- Photonics Science camera was tested.
- Trouble with the motion loop in XTD2 and XTD10, reported to AE.
AE (P. Gessler ):
- MCP motion and k-monochromator were tested.
- Motion loop was split in SASE1 tunnel.
- Many tests, lots of work in progress, need to act quick as time is short.
- T. Wilksen (DESY) is going to update the timing hardware è devices would have to switch to local timing, and switch back later to be operable.
Laser (M. Lederer):
- Further commissioning of the PP-laser was started.
- Upgraded Karabo and PLC firmwares. Works are on schedule.
- Measurements on the dependence of humidity are ongoing.
- DESY is working on the timing system, laser synchronization will be down until the 21.1.18.
- PP-laser pattern selection with machine timing:DESY is now pushing for the originally planned implementation. DESY will have to do some software development in this context.
Detectors (J. )
- Tested the AGIPD @ SPB, but 1 board was not working. Detector consortium could not provide a replacement board, so only half of the detector was tested before SPB/SFX had to close the detector vessel again.
- LPD was tested with train builder, but only tests using 2 memory cells could be conducted (2 images per train), so train builder was not tested with all memory cells.
- More tests with full load (i.e up to 510 images per train) still have to be performed.
- Test with DSSC will take place in HERA South in CW 51.
ITDM (K. Wrona)
- Monday til Wednesday there will be no DAQ due to extension of the Infini-band bandwidth, upgrades, firmware updates, recabling etc.
- DAQ up again on Thursday
Software (S. Brockhauser)
- CAS-People are currently working only in SASE3. In the future, they can either work on SASE3 or SASE2, but not both!
- Slides with Project-plan provided by Hugo Santos (see Indico)
- Release of Karabo 2.2.0 on the 18.12. (in the meantime shifted to the 20.12.)
- Testing by ITDM and consecutive deployment in tunnels and at the instruments takes until 22nd of January
- Karabo 2.2.1 to be expected mid of January
- Further decisions will be taken mid of January
|