Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 427
Entry time: 01 Dec 2017, 11:42
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1 Status/SASE3 Readiness Meeting |
|
|
General:
- User Operation ongoing until Tuesday 5 Dec 8 AM
- CAS shall present a release plan for KARABO 2.2 next week
- Dispatch meetings shall move to a Mo/Wed 13:00 schedule starting next Wedneday 6 Dec
Instruments
- FXE:
- Scantool was successfully used to establish overlap with laser beam (Tangerine)
- Some problems with slow DAQ in particular also for tunnel components
- Comment from ITDM: There are known issues with the slow data acquisiton. A new version exists that was intentionally not deployed before the end of UOP
- SPB
- Just finished first shift of laser user experiment
- No big problems
- All goals in the optimistic schedule were achieved
Tunnels
- Currently preparing for the shutdown
- Sticking condition of mirror bender could be reproduced in the lab
- WP74 just installed the last missing pieces in XTD1
Laser
- Running
- temporal and spatial overlap with beam is achieved
- But now instruments do not intend to use the PP laser for the last experiment
Detectors
- Both detectors are working
- The DAQ for slow data is crashing occasionally
- Gotthard is fully operational but there problems getting the data out. Help from PSI is needed
AE
ITDM
CAS
- CAS-XPD Running:
- We will finish next Monday
- We have been addressing issues related to MCP, Karabo-DAQ, Cameras, and K-Mono
- Deploy K-mono today
- Review DAQ Groups in Karabo: Cyril (interface to ITDM), Liubov, Koch
- Gotthard we have to address in a separate and more systematic discussion: trigger, operation, calibration...
- XGM memleak - we already have a fix to get it stable but have to check when we will be able to upgrade (only device).
- Internal discussion about CAS/Karabo priorities for the winter shutdown
|