Group Selection Page
HELP
Controls Group
ITDM
DET
Vacuum
WP78
FXE
SPB
HED
SQS
SXP
Sample Environment
PSPO
XO
TS
Migrated2Zulip
Archived2GitlabPages
Archived2PDF
MigratedByGroup
|
|
SASE1 Status and SASE3 Readiness
|
| Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
|
Message ID: 507
Entry time: 13 Apr 2018, 09:40
|
| Author: |
Adriano Violante |
| Location: |
XHEXP |
| Severity: |
Information |
| Subject: |
Emergency off test in SPB/FXE |
|
|
Emergency power test will be performed at the following dates:
FXE - Mon. 16.04.
SPB - Tue. 17.04.
Schedule
- 10:00 Power will go off in SASE1 - Only redundant power line will stay ON
- Reprogramming of the PLC of the Emergency power off system - Estimated 1.5 Hrs.
- Power ON again ==> Emergency OFF test will be carried out. (info from AE: AE PLCs will not go off. uTCA crates will be shut down before)
- About at 15:00 everything should be back to normal.
For technical questions contact T. Schoen and U. Brueggmann. |