Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
SPB
SQS
XO
ToBeMigrated2XWiki
ToBeMigrated2GitlabPages
ToBeMigratedByGroup
Migrated2Zulip
Archived2PDF
not2MigrateOrArchive
SCS
SXP Migrated2Zulip
Photon Commissioning Team
XRO
DOC
HED Migrated2Zulip
WP74
MID
PSPO_XO
XO_Operation
SQS Migrated2Zulip
FXE Migrated2Zulip
DET
Sample Environment
SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness
Technical integration and coordination
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
578
Entry time:
14 Nov 2018, 10:23
Author:
Adriano Violante
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 09.30
SPB
Lopp 5 update - will be agreed between SPB and AE
Smaract limit switches issues - AE will have a look. In the meanwhile also the company of the controlles has been asked by SPB
KB motor steps have different size with respect to encoders. This issue is known and a workaround / solution has to be discussed with AE offline
Pulse picker will be used and commissioning finalized.
Sample chamber encoder drift issue. Hasx to be investighated further. AE can support.
FXE
SQS
S
CS
MID
HED
XPD
VAC
AE
MID Loop 11 - Fw received. Being tested.
PLCs for optical lasers in SASE3 and 2 control being set up
SASE3 support for commissioning ongoing