SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 578     Entry time: 14 Nov 2018, 10:23
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Lopp 5 update - will be agreed between SPB and AE
  • Smaract limit switches issues - AE will have a look. In the meanwhile also the company of the controlles has  been asked by SPB
  • KB motor steps have different size with respect to encoders. This issue is known and a workaround / solution has to be discussed with AE offline
  • Pulse picker will be used and commissioning finalized.
  • Sample chamber encoder drift issue. Hasx to be investighated further. AE can support.

FXE

SQS

SCS

MID

HED

XPD

​​VAC

AE

  • MID Loop 11 - Fw received. Being tested.
  • PLCs for optical lasers in SASE3 and 2 control being set up
  • SASE3 support for commissioning ongoing 

ITDM

CAS

AoB