SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 28     Entry time: 27 Jan 2017, 09:25
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Software Report 

Post on behalf of S. Brockhauser

 Since I am in Grenoble and visiting ESRF, I will not be able to give you the report in person. Instead Alessandro can give you a Summary.

In fact:
- we did collect the full list of the Karabo names for all the equipments involved
- we have started our sprint and we are on track
As next things:
- we are collecting all the required Karabo(!) default parameters
- we plan to finish the sprint as planned and presented last time.
Until now we have not experienced and obstacle.

Best wishes
Sandor