Hi everyone,
there was some miscommunication between us and DESY: only the Timing firmware and doocs server need to be updated, the RTM was already been replaced. This require update is similar to the one perform two weeks ago (see entry #449).
The time slot for this update is next Wednesday, 23rd January, between 16h and 17h. The update will affect all Timing Devices in SASE1. This operation should not take more than 10 minutes; during this time no timing signals will be generate (clocks/triggers/bunch patterns/etc.). Naturally, problems may occur during this update which will lead to increase down time.
If somebody sees a problem with the current schedule, please contact me.
Adriano Violante wrote: |
General remarks:
- Stable beam only to be expected starting from 1.03. for SASE1 instruments commissioning
- There is no guarantee for parasitic beam delivery to the experiments. If it happens at all it will most probably be during the last week of Feb. This has to be agreed on the fly with the BKR and H.S/ T.T.
SPB/SFX:
- Preparing D.02 for mirrors installation (next week)
- Karabo being updated
Advanced Electronics:
- Trigger delivered by DESY should be back and stable at 10Hz.
- ATM for timing has to be replaced in the balcony rooms. Bruno Fernandes is trying to find a way to reduce the downtime down to 30 minutes. Will be scheduled in the next days.
ITDM:
- 1 line card has to be replaced. Probably happens on Wednesday this week during the DAQ tests.
- Tuesday afternoon the online storage units will me remounted with the same path of the offline ones.
- This week a proposal for the in-house commissioning is going to be circulated.
|
|